Fit-out constraints
Discipline-specific rules for Unit 22-04

Constraints reflect KAFD base-build specification and tenant guidelines. Items marked for review require consultant input before sign-off.

Plumbing constraints
1 item under review
Max horizontal waste run4.5 m
Min slope1:80
Permitted wet zonesPantry, WC core only
Booster pumpNot permitted in tenant area
Partition wall constraints
Within rules
Max partition height2.8 m
Slab-to-slab fixingNot permitted
Acoustic minimum42 dB Rw
Ceiling grid coordinationRequired
ICT / data cabling constraints
Within rules
StandardCAT6A minimum
Containment fill ratioMax 40%
Floor box densityMax 1 per 9 m²
Patch panel terminationFloor IDF only
HVAC constraints
1 item under review
VAV reconfigurationRequires base-build approval
Diffuser relocationPermitted within zone
Supplementary coolingAllowed in IT rooms only
Boardroom design density1 person / 2.5 m²
Fire and life safety constraints
Awaiting review
Sprinkler relocationRequires fire engineer sign-off
Travel distanceMax 30 m to nearest exit
Smoke detector spacingPer base-build grid
Fire-rated partitionsRequired at corridors
Access control constraints
Within rules
Reader typeKAFD-approved encrypted readers
Tenant doors per readerMax 1
IntegrationKAFD building system mandatory
Emergency overrideRequired at all secure doors